Traffic changes on Kings Way

Ahead of major construction for the Metro Tunnel Project, changes to the road, tram and bicycle networks of Kings Way are required to keep Melbourne moving during construction.

As the major arterial route in the precinct, Kings Way has been identified as the primary diversion route during construction of the new Anzac Station. To ensure Kings Way can cater for the predicted increase in traffic, it is essential that changes are made to the road to improve the efficiency of the network.

A number of intersections along Kings Way will be upgraded to improve the traffic flow, efficiency and the safety of the network for vehicles, cyclists and pedestrians.

Commencing early January 2018, works will largely be undertaken during off-peak traffic periods, concurrently, or be staged to occur at variable times to minimise traffic disruptions. There may be periods of medium level noise with construction and activities, all managed in accordance with Metro Tunnel Project Environmental Performance Requirements (EPRs) (PDF, 1.2 MB).

Advance notification for motorists, pedestrians, and cyclists traffic conditions and detours will be provided using signage and traffic management.

Road works and changes

January to late February 2018

Changes will be made to the intersection of Kings Way and Park Street to increase the capacity and efficiency of Kings Way while investigation works confirm service location and depth in the area. Impacts include:

  • Modifying service road kerb, to become a "left turn only" lane.
  • Line marking works.
  • Installing overhead traffic signs across Kings Way north-west of Cobden Street to support changed traffic conditions.
  • Constructing an exit point for vehicle traffic on Kings Way north-west of Cobden street from the service lane into the slow lane in the carriageway on Kings Way.

These night works will take place at the following times:

  • Service investigation works: 3 - 12 January, 6pm - 7am.
  • Kings Way service lane near Cobden Street intersection: 3 - 19 January, 6pm - 7am.
  • Park Street and Kings Way intersection: 10 January - 15 Febrary, 6pm - 7am.

  • Intersection of Kings Way & Park Street

Late February to late March 2018

Changes will be made to the intersection of Kings Way and Albert Road to better define lanes and encourage greater use of the outer lanes. Impacts include:

  • Line marking and installation of overhead signage.
  • Installing a 40km speed zone near Mac Robertson Girls' High School.

These works will be undertaken at night to minimise traffic disruptions.


Intersections of Kings Way & Albert Road and Kings Way & Queens Road

Late February to late March 2018

Changes will be made to the slip lane from Kings Way onto Queens Road and at pedestrian crossings in the vicinity of the intersection, as well as installation of traffic signage to support changes to traffic movement. Impacts include:

  • Service investigation works to confirm service location in the area.
  • Improvements to pedestrian crossing.
  • Borehole drilling and geotechnical investigations to determine ground conditions.
  • Installing an overhead gantry with a traffic sign.

These works will be undertaken at night to minimise traffic disruptions.


Intersections of Kings Way & Albert Road and Kings Way & Queens Road

January to late February 2018

Changes will be made to the intersection of Kings Way, York Street, and Coventry Street including changes to traffic signals at the intersection of the Domain Tunnel off-ramp and Kings Way. Impacts include:

  • Road resurfacing works on Kings Way from York Street up to the West Gate Freeway.
  • Constructing new kerb outstands at the York Street intersection.
  • Constructing a new centre median at the Coventry Street intersection.
  • Asphalting and new line marking on Kings Way, from York Street up to the West Gate Freeway.

These night works will take place at the following times:

  • Service investigation works: 3 - 12 January, 6pm - 7am.

Intersection of Kings Way & York Street

January to late February 2018

Changes will be made to the intersection of Dorcas Street and Tope Street for service investigations works. Impacts include:

  • Constructing new kerb outstands and landscaping.
  • Line marking.

These works will take place at the following times:

  • 7am - 6pm, Monday to Friday.
  • 7am - 1pm, Saturdays.

Intersection of Kings Way & York Street

January to late February 2018

Changes will be made to Eastern Road for service investigation works. Impacts include:

  • Constructing a centre median within Eastern Road.

These works will take place at the following times:

  • 7am - 6pm, Monday to Friday.
  • 7am - 1pm, Saturdays.

Intersection of Kings Way & York Street

Download this information as a fact sheet (PDF, 2.4 MB).