Construction in the St Kilda Road precinct

Anzac Station is strategically placed to ease pressure on the St Kilda Road / Swanston Street tram corridor and will significantly improve access to key Melbourne landmarks such as the Shrine of Remembrance and Albert Park.

Current work notifications

Start date

Where

What is happening?

Until late December 2017

St Kilda Road

Water works

St Kilda Road will be reduced to one lane southbound from Domain Road to Bromby Street

Melbourne Grammar School’s driveway will be accessible via St Kilda Road under traffic management, however, visitors will be encouraged to use the Bromby St driveway during these works.

There will be periods of medium to high-level noise associated with excavation of the three manholes, saw cutting the road and open cut trenching.

For more information, see the (local sewer diversion and water main works in Domain notification PDF, 677.4 KB).

Gas commissioning works

St Kilda Road will intermittently be reduced to one lane in the city-bound direction between Kings Way and Bowen Crescent.

The St Kilda Road intermittent lane closures will be in place for approximately 20 days while major gas decommissioning works are carried out in the roadway to make way for a new underground station at Domain.

More information: Traffic changes in Domain

May

UPDATED 11 December

Albert Road

South Yarra main sewer relocation works and service investigations. Impacts include:

  • These works will require the short-term closure of the left turn lane from St Kilda Road onto Albert Road for the duration of works
  • The car parks on the southern leg of Albert Road at the Kings Way end will only be accessible via Kings Way for the duration of works via the u-turn facility
  • Following the completion of works, westbound traffic movement through the northern leg of Albert Road will be reinstated
  • There may be periods of medium to high-level noise associated with these works. Impacts from noise will be managed in accordance with the Metro Tunnel’s Environmental Performance Requirements
  • Line marking activities will be carried out at night. This activity is expected to produce only low levels of noise.

Download notification: South Yarra Main Sewer (PDF, 738.6 KB)

7 December

Park Street, South Melbourne

Until 23 December 2017, Yarra Trams will be undertaking ground investigation work and installing new tram poles and overhead tram power cables to relocate the Park Street, South Melbourne tram stop.

Works will include:

  • Saw cutting pavement and potholing
  • Excavation of the pole holes and concreting foundations along Park Street using non-destructive digging
  • Pole erection using specialised crane and equipment and concreting the poles into place
  • Clean up and reinstatement of footpaths
  • Overhead tram power cables and support system works.

Night Works will be required to minimise the impact to traffic due to roadside installation work and will take place between 7pm – 5am, from 11 - 21 December, with the exclusion of Friday 15 December and Saturday 16 December.

For more information see the Tram pole installation works notification (PDF, 872.1 KB).

19 November until early December

Kings Way

Changes to the road network, which will include night works. Works will be staged in order to minimise impacts on traffic.

There may be periods of medium level noise.

For more information, see the Changes to Kings Way notification (PDF, 4.1 MB).

26 October

Market Street, South Melbourne

Preparations for road upgrades and the establishment of a site compound, with the following impacts:

Approximately nine car parking spaces at the Kings Way end of Market Street will be occupied while this site compound is in place

There will be traffic management measures in place around the site compound

Traffic will still be able to turn left from Tope Street into Market Street and right from Market Street into Tope Street.

For more information: see the Market Street notification (PDF, 1.1 MB).

17 October

Bowen Crescent

There will be periods of medium to high-level noise associated with excavation of the three manholes, saw cutting the road and open cut trenching. This will require the short term occupation of kerbside car parking

From late October Bowen Crescent will be closed to eastbound traffic between St Kilda Road and Queens Lane with localised detours in place.

For more information, see the (local sewer diversion and water main works in Domain notification PDF, 677.4 KB).

Until late November

Bowen Lane

Gas commissioning work including footpath and road closures. There will be medium to high-level noise associated with these works.

This will require the short term occupation of kerbside car parking.

Bowen Lane will be closed for one day in October.

Download notification: Gas commissioning works overview (PDF, 1003.5 KB)

10 October

Edmund Herring Oval

Construction of a temporary power substation on the southern end of Edmund Herring Oval, close to Domain Road. This substation will provide power for the tunnel boring machines required to build the Metro Tunnel.

A temporary site compound will be established to support construction activities

The irrigation main located on the south side of Edmund Herring Oval will be relocated to protect it during the works.

Download notification: Construction of a temporary electrical substation (PDF, 4.1 MB)

28 August

UPDATED 25 September

Bowen Crescent

Gas main works, which will have the following impacts:

  • From 25 September, the eastbound lane on Bowen Crescent will be closed
  • In early October to mid-October, the westbound lane of Bowen Crescent will be closed.
  • During these works, there will be approximately three days when access to the Botanica St Kilda Road driveway will be impacted from 9am - 3pm. Residents will be provided with 48 hours advance notification ahead of these works.
  • Up to 11 car parking spaces will be temporarily occupied during this work.
  • All non-residential eastbound vehicular traffic on Bowen Crescent will be diverted around our worksite via Queens Lane, while westbound traffic will be maintained. Please refer to signage in the area.
  • There will be medium to high-level noise associated with these works.

For more information:

12 July

UPDATED for works starting 20 September

Domain Road

South Yarra Main Sewer works in Domain Road will require:

  • From 20-22 September construction hours will be extended until 10pm
  • shaft construction, tunnelling and connection of the new sewer
  • Medium to high-level noise will be generated by these works
  • Excavated material will be stored on site during construction hours and removed during the day

Domain Road is now closed between St Kilda Road and the western edge of Edmund Herring Oval for approximately five years – extending beyond the duration of sewer works

Download notification:

28 August

Domain Street

Gas commissioning works at both ends with traffic maintained. There will be medium to high-level noise associated with these works.

Download notification: Gas commissioning works overview (PDF, 1003.5 KB)

28 August

Park Street

Tram pole installation works

Gas service relocation

  • Park Street gas works will involve closing the left turn lane from Park Street into Wells Street
  • Lane closures and parking lane impacts for the required service investigation works
  • Partial closure of the footpath on Park Street adjacent to the Park Street frontage of 380 St Kilda Road
  • There will be medium to high-level noise associated with these works.

Download notification: Gas commissioning works overview (PDF, 1003.5 KB)

Until January 2018

South African Soldiers Memorial

The removal of the South African Soldiers Memorial and the John Cockbill Memorial Drinking Fountain.

The removal and storage activity will be overseen by a Heritage Victoria approved Heritage Conservation Consultant and carried out by suitably qualified specialists within this field.

Some car parks will be temporarily removed to allow workers access to the site.

There will be periods of medium to high-level noise and some night works may be required.

Download notification: South African Soldiers Memorial removal notice (PDF, 610.8 KB).

Overview of current works

Service relocation works in this area include the relocation and protection of over 100 underground utility services such as water, gas, power and telecommunications.

About the new station

Anzac Station will be an important interchange between train and tram services on St Kilda Road.

The new station will serve thousands of people destined for the employment and residential precinct along St Kilda Road every day, and support the continuing growth and redevelopment of the South Melbourne / Kings Way precinct. Read more about Anzac Station.

The preferred station location is the result of detailed investigations, design and planning by engineers, transport modellers and other experts with experience on rail tunnels and other infrastructure projects in Australia and around the world.

Anzac Station will be built via a 'cut and cover' method, with the station box excavated from the top down and a roof slab placed over the top of the site.

Underground construction activities will take place 24/7 once the roof slab and appropriate acoustic treatments have been installed while traffic and trams continue to flow on St Kilda Road. Read more about building Anzac Station.