Skip to main content
Metro Tunnel

Construction at Kensington

Building the western tunnel entrance involves construction works on Childers Street to build a retaining wall that will support the embankment on the northern side of the rail corridor (east of Kensington Road), which is to be widened to accommodate the new Metro Tunnel tracks.

A decline structure is being built so trains can enter the new Metro Tunnel.

The tunnel entrance structure is proposed to be built via a 'cut and cover' method, which will see them excavated from the top down and the surface then reinstated over the top of the tunnels.

A construction support site on Hobsons Road and a tunnel boring machine (TBM) retrieval box have been built to support tunnelling works.

It is not proposed that any construction activities for the Metro Tunnel Project will be undertaken in JJ Holland Park, other than potential upgrades to the shared use path.

See Kensington Precinct Works Notifications for details of current works in Kensington.

Construction work at Kensington

Construction look ahead For 2020/2021

Current Works

Worksite Map 2020

What we are doing

Diaphragm wall (D-Wall) construction

  • Construction of two, 280-metre D-walls consisting of over 200 individual panels
  • Two large cranes excavating individual panels, up to 20 metres deep and one crane excavating rock and firmer soils at the bottom of the excavation
  • Use of the temporary bentonite plant in Hobsons Road to mix, pump and recycle bentonite while D-wall works take place
  • For more information about D-Wall construction, see our fact sheet

Tunnel entrance excavation and base slab construction

  • Earthworks to construct new access ramps and a stable working platform within the tunnel entrance
  • Construction of base slab including installing drainage pipes and pits, installing waterproofing material, placing steel and pouring concrete
  • Breaking back D-walls to connect base slab steel into the steel of D-Wall panels
  • Removing excavated material using excavators and trucks

TBM breakthrough and retrieval

In mid-February, the first Tunnel Boring Machine (TBM), Joan, arrived at the TBM retrieval shaft adjacent to South Kensington station. In mid-March, the second TBM, Meg, also arrived and broke through into the shaft at Childers Street.

When the TBM cutterhead ‘broke through’ into the retrieval shaft, the shaft was filled with water to balance groundwater levels while the final section of the tunnel is constructed. After the water was drained, the TBM cutterhead was retrieved. Water was pumped back to the water treatment plant at the Arden Station site via the TBM.

The TBM cutterhead and front shield sections were cleaned and disassembled using high pressure cleaners and hand tools before being removed from the retrieval shaft and loaded onto trucks using a crane.

The rear (gantry) sections of the TBM travelled back to the Arden Station site through the constructed tunnel.

Each TBM took approximately four weeks to retrieve. Oversized TBM pieces were transported at night to Arden Station.

See Tunnel Boring Machines for details of how TBMs work and the works notification (PDF, 456.2 KB) for more information on the breakthrough.

TBM breakthrough at Kensington